EN
CN
The Hydrocyclone Skid for CNOOC's Weizhou 12-2 Platform Project has safely arrived at the project site
From: Time:2024-12-24 Read:44

In August 2023, our company was again awarded a contract to supply a Hydrocyclone Skid (comprising 4 units on a single skid) for CNOOC's Weizhou Oilfield Cluster Production Processing Center Capacity Optimization Project.

Due to delays in the overall platform construction schedule, and in accordance with the owner's final requirements, the Factory Acceptance Test (FAT) for this project was conducted at our manufacturing facility on December 6, 2024, with participation from the owner's team, China Classification Society (CCS), and Chenglu Environmental Engineering Corporation (CEEC).

 

On the evening of December 24, 2024—Christmas Eve—the project equipment was safely shipped to the owner's designated Tianjin Binhai Offshore Construction Site for subsequent installation and commissioning.