Products of Malaysia ATB-PU Project Enters the Installation Stage
From:CEEC Time:2021-03-15 Read:655

Recently, the equipment of Malaysia ATB-PU wastewater treatment project signed by Chenglu and China Huanqiu Engineering Co., Ltd. Southeast Asia Branch has been accepted by the third party, and has been delivered to the ATB project site in succession. The site has been accepted smoothly and the installation is in full swing.

The owner of wastewater treatment plant of Malaysia ATB-PU project is ATT Tanjung Bin Sdn Bhd (ATB), and the general contractor is China Huanqiu Engineering Co., Ltd. (HQC). This project is a key project of China Huanqiu Engineering Co., Ltd. Southeast Asia branch in Southeast Asia. Our company undertakes the design, procurement, supply, installation guidance and commissioning of sewage treatment station of this project. The project design has been approved by PMC (Worrley India), the processed products have been accepted by Intertek Moody, SGS and other third parties, and the related products have obtained DOSH certification in Malaysia.

包装照片

发运照片

深度处理项目安装现场

预处理框架项目安装现场

 

The capacity of the project is 600m3/d. The wastewater comes from atmospheric and vacuum production wastewater, electric desalting wastewater and electric desalting cleaning wastewater. The wastewater treatment plant of ATB-PU project adopts full American standard design, and our company's designers work overtime. In the design process, PDMS, SolidWorks and other software are used to carry out fine design for the wastewater treatment plant system and products to meet the requirements of international high standards. At present, the project has been initially delivered, and it will enter the commissioning stage when the installation is completed.